Period Renovation Blog Part 10: Updating Old Flooring

Build It expert Alan Tierney
by Alan Tierney
19th January 2020

When we started the renovation, the home had solid concrete floors, which meant that most of the ground floor was not insulated and ground water was often pushed up through the base of the wall.  As a result the house was uncomfortably cold and damp. Replacing these with warm and breathable solid flooring was a major part of the refurbishment project.

Period Renovation Project 9: Fixing unsafe features

Flooring in period property

The dining room floor starts coming up

We began by breaking up and removing the concrete layer. This was different in each room; the dining room was just concrete laid directly on the earth. The sitting room was a more lightweight screed with a plastic damp proof membrane; the kitchen was similar but covered with vinyl tiles.

Man plastering a wall

Base coat plaster using earth dug from the floor

As part of our strategy for minimising waste we have saved the broken up material from the dining room and sitting room for use as hardcore for external landscaping. Unfortunately the vinyl tiles meant the kitchen floor was too contaminated and we had to send it to the skip.

Man breaking up the floor in a period renovation

Breaking up the kitchen floor

The next stage was to excavate the sub-floor a further 150-175mm to allow the installation of an insulation and vapour control layer.

In the dining room this involved digging out clay-rich earth, which proved ideal for sieving and mixing to make clay plaster. Rather than shift all the material out of the house and then bring plaster back in later I simply mixed it in situ as I went along and applied it straight on to the walls as the base coat plaster. I think that must be the shortest supply chain possible!

Broken up floor screed

Remains of the kitchen floor screed

The kitchen and sitting room had a sting in the tale – rather than nice soft earth, they were mostly bedrock. This needed to be broken up with a heavy duty breaker, laboriously dug out and shifted by wheelbarrow. It was an arduous and pretty thankless task but has generated a large pile of stone that will come in handy later in the project.

Bedrock

The bedrock below the floors

Once the excavation was complete we lined the space with geotextile membrane and back filled with foamed glass aggregate. Once compacted to a thickness of 150mm this will provide a solid base for the finished floors to be built up. It is an insulating layer, improving thermal comfort and allowing us to install underfloor heating.

Man excavating bedrock

Tackling bedrock with a breaker

Finally the foamed glass forms a capillary barrier to rising moisture, buffering any damp from ground water. This is much more compatible with a traditional, solid walled building than a conventional membrane and will not force water to the base of the walls.

Man digging up broken rock

Digging up the broken rock

The next stage is to start first fix plumbing and electrics, running pipes and cables in the sub-floor. Then there will be another layer of geotextile with the underfloor heating pipes over that, followed in the kitchen by a lime screed, then a granite floor.

Man pouring foamed glass aggregate
Adding the foamed glass aggregate
Layer of foamed glass aggregate
Complete foamed glass aggregate

Period Renovation Blog 11: Applying for Listed Building Consent

The dining room and sitting room will be finished with earth floors, using material from the site. We need to test the durability of these; it’s not something I have done before. All the information I have found seems to suggest that they will be fine, but we have a fallback of finishing with ceramic tiles if necessary.

One Comment

  1. John Williamson says:

    Wonderful blog Alan. We’re in the process of going through a very similar process with my 1800 listed building.

    Just wondered if you could share the makeup of the floor. Assuming this is Limecrete? You mentioned 150mm of compacted foamed glass, how thick was the Limecrete on top and what ratio of NHL 5 to sharp sand did you use?

Leave a Reply

You may be interested in

Our sponsors